Assessment Year | 2016 |
---|---|
Principal Product | Carbonated Beverages |
NAICS | 312111: Soft Drink Manufacturing |
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | greater than $500 M |
# of Employees | 1,000 |
Plant Area |
200,000
ft2
|
Annual Production | 62,400
Tgal
|
Production Hrs. Annual | 6,006
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $715,588 | 10,624,770 |
kWh
|
$0.067 |
Electricity Demand | $113,938 | 25,627 |
kW-mo/yr
|
$4.45 |
Electricity Fees | $3,601 | - |
|
- |
Natural Gas | $152,739 | 34,176 |
MMBtu
|
$4.47 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $169,275 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $93,995 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $11,140 | - |
$11,140
166,300
kWh
|
- | - | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,860 | $2,250 |
$3,450
51,510
kWh
|
$410
-
kW-mo/yr
|
- | - | |
03 | 3.4113: Treat and reuse rinse waters | $34,545 | $41,405 | - | - | - |
$34,545
-
gal
|
|
04 | 2.2694: Use highest temperature for chilling or cold storage | $8,290 | $11,760 |
$7,320
109,300
kWh
|
$970
-
kW-mo/yr
|
- | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $48,630 | $79,420 |
$39,060
582,930
kWh
|
$9,570
-
kW-mo/yr
|
- | - | |
06 | 2.7232: Replace existing hvac unit with high efficiency model | $14,700 | $44,740 | - | - |
$14,700
-
MMBtu
|
- | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $22,170 | $77,500 |
$19,820
295,820
kWh
|
$2,350
-
kW-mo/yr
|
- | - | |
08 | 2.2437: Recover waste heat from equipment | $14,500 | $53,850 |
$6,300
94,080
kWh
|
- |
$8,200
-
MMBtu
|
- | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,440 | $46,960 |
$10,100
150,680
kWh
|
$1,340
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $169,275 | $357,885 |
$97,190
1,450,620
kWh
|
$14,640
-
kW-mo/yr
|
$22,900
-
MMBtu
|
$34,545
-
gal
|
||
TOTAL IMPLEMENTED | $93,995 | $210,605 |
$41,060
612,800
kWh
|
$3,690
-
kW-mo/yr
|
$14,700
-
MMBtu
|
$34,545
-
gal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs