ITAC Assessment: DL0155
ITAC logo
ITAC Assessment: DL0155
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Architectural Glass
NAICS 327211: Flat Glass Manufacturing
SIC 3211: Flat Glass
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 108,000
ft2
Annual Production 2,000,000
lb
Production Hrs. Annual 2,700
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $73,534 1,210,193
kWh
Electricity Demand $42,287 7,120
kW-mo/yr
Natural Gas $10,378 1,227
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,315 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,190

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.6212: Turn off equipment during breaks, reduce operating time $3,690 - $550
5,305
kWh
- $3,140
-
MMBtu
02 2.6212: Turn off equipment during breaks, reduce operating time $500 - $500
4,875
kWh
- -
03 2.6212: Turn off equipment during breaks, reduce operating time $8,960 $6,880 $8,960
87,010
kWh
- -
04 2.7424: Shade windows from summer sun $1,760 $6,840 $1,760
17,100
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $3,405 $13,615 $2,710
26,270
kWh
$695
-
kW-mo/yr
-
TOTAL RECOMMENDED $18,315 $27,335 $14,480
140,560
kWh
$695
-
kW-mo/yr
$3,140
-
MMBtu
TOTAL IMPLEMENTED $4,190 - $1,050
10,180
kWh
- $3,140
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs