Assessment Year | 2014 |
---|---|
Principal Product | Silicone rubber composites and adhesives |
NAICS | 325199: All Other Basic Organic Chemical Manufacturing |
SIC | 2822: Synthetic Rubber (Vulcanizable Elastomers) |
Sales Range | $50 M to 100M |
# of Employees | 120 |
Plant Area |
129,220
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Delaware |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $673,019 | 7,488,041 |
kWh
|
$0.090 |
Natural Gas | $418,876 | 49,933 |
MMBtu
|
$8.39 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $193,750 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $102,620 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $36,000 | $33,600 |
$36,000
400,000
kWh
|
- | - | |
02 | 2.2622: Replace existing chiller with high efficiency model | $41,430 | $54,000 |
$41,430
460,300
kWh
|
- | - | |
03 | 2.7241: Install outside air damper / economizer on hvac unit | $16,580 | - |
$16,580
184,200
kWh
|
- | - | |
04 | 2.2711: Utilize outside air instead of conditioned air for drying | $4,630 | $5,700 |
$1,910
21,250
kWh
|
$2,720
-
MMBtu
|
- | |
05 | 3.4114: Replace city water with recycled water via cooling tower | $54,210 | $28,110 | - | - |
$54,210
-
Tgal
|
|
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,090 | $10,500 |
$9,090
101,000
kWh
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $23,200 | $13,590 |
$23,200
257,400
kWh
|
- | - | |
08 | 3.4155: Meter waste water | $8,610 | $8,200 | - | - |
$8,610
-
Tgal
|
|
TOTAL RECOMMENDED | $193,750 | $153,700 |
$128,210
1,424,150
kWh
|
$2,720
-
MMBtu
|
$62,820
-
Tgal
|
||
TOTAL IMPLEMENTED | $102,620 | $95,800 |
$94,010
1,044,500
kWh
|
- |
$8,610
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs