Assessment Year | 2014 |
---|---|
Principal Product | Utility Plant |
NAICS | 221330: Steam and Air-Conditioning Supply |
SIC | 3999: Manufacturing Industries, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 16 |
Plant Area |
48,313
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Maryland |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,681,559 | 37,961,072 |
kWh
|
$0.071 |
Natural Gas | $1,372,391 | 261,114 |
MMBtu
|
$5.26 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $252,790 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $134,000 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.1231: Establish burner maintenance schedule for boilers | $4,734 | $1,000 | - |
$4,734
-
MMBtu
|
|
02 | 2.2628: Utilize a less expensive cooling method | $16,470 | $4,000 |
$16,470
233,298
kWh
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $97,586 | $350,000 |
$97,586
1,382,240
kWh
|
- | |
04 | 2.4112: Install soft-start to eliminate nuisance trips | $134,000 | $150,000 |
$134,000
1,898,000
kWh
|
- | |
TOTAL RECOMMENDED | $252,790 | $505,000 |
$248,056
3,513,538
kWh
|
$4,734
-
MMBtu
|
||
TOTAL IMPLEMENTED | $134,000 | $150,000 |
$134,000
1,898,000
kWh
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs