Assessment Year | 2012 |
---|---|
Principal Product | Clean Water |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | less than $500 k |
# of Employees | 6 |
Plant Area |
652,400
ft2
|
Annual Production | 730,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Maryland |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $201,532 | 2,467,200 |
kWh
|
$0.082 |
Electricity Demand | $17,041 | 5,142 |
kW-mo/yr
|
$3.31 |
Natural Gas | $78,819 | 6,874 |
MMBtu
|
$11.47 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $337,014 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,014 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,066 | $12,089 |
$2,066
21,497
kWh
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,900 | $11,930 |
$2,900
35,400
kWh
|
|
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,698 | $17,843 |
$6,698
81,687
kWh
|
|
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,410 | $100 |
$2,410
29,400
kWh
|
|
05 | 2.2211: Use optimum temperature | $2,940 | $100 |
$2,940
35,800
kWh
|
|
06 | 2.1336: Install equipment to utilize waste fuel | $320,000 | $3,600,000 |
$320,000
11,169,000
kWh
|
|
TOTAL RECOMMENDED | $337,014 | $3,642,062 |
$337,014
11,372,784
kWh
|
||
TOTAL IMPLEMENTED | $17,014 | $42,062 |
$17,014
203,784
kWh
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs