ITAC Assessment: DL0096
ITAC logo
ITAC Assessment: DL0096
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Circuit Boards
NAICS 334418: Printed Circuit Assembly (Electronic Assembly) Manufacturing
SIC 3661: Telephone and Telegraph Apparatus
Sales Range $10
M
to 50
M
# of Employees 68
Plant Area 32,000
ft2
Annual Production 100,000
pieces
Production Hrs. Annual 4,680
hrs
Location (State) Maryland

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $176,130 1,535,988
kWh
Natural Gas $9,782 1,216
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,458 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,692

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $6,429 $30,095 $6,429
55,425
kWh
-
02 2.2437: Recover waste heat from equipment $1,176 $8,000 - $1,176
-
MMBtu
03 2.6125: Keep equipment clean $2,296 $1,200 $575
4,960
kWh
$1,721
-
MMBtu
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,791 $500 $2,791
24,062
kWh
-
05 2.2135: Repair and eliminate steam leaks $766 $270 $766
6,600
kWh
-
TOTAL RECOMMENDED $13,458 $40,065 $10,561
91,047
kWh
$2,897
-
MMBtu
TOTAL IMPLEMENTED $12,692 $39,795 $9,795
84,447
kWh
$2,897
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs