ITAC Assessment: DL0046
ITAC logo
ITAC Assessment: DL0046
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Molded Rubber
NAICS 326299: All Other Rubber Product Manufacturing
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 40
Plant Area 50,000
ft2
Annual Production 4,450,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) Maryland

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $125,455 1,090,486
kWh
Natural Gas $60,953 4,822
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,602 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,082

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.6218: Turn off equipment when not in use $4,503 - $4,503
40,209
kWh
-
02 2.6218: Turn off equipment when not in use $2,940 - $2,940
18,200
kWh
-
03 2.2511: Insulate bare equipment $7,292 $520 $7,292
65,120
kWh
-
04 2.4231: Reduce the pressure of compressed air to the minimum required $4,168 $1,500 $4,168
37,208
kWh
-
05 2.1233: Analyze flue gas for proper air/fuel ratio $7,619 $10,000 - $7,619
-
MMBtu
06 2.7142: Utilize higher efficiency lamps and/or ballasts $12,295 $23,738 $12,295
109,780
kWh
-
07 2.3512: De-energize excess transformer capacity $785 $2,410 $785
7,012
kWh
-
TOTAL RECOMMENDED $39,602 $38,168 $31,983
277,529
kWh
$7,619
-
MMBtu
TOTAL IMPLEMENTED $24,082 $35,238 $16,463
146,988
kWh
$7,619
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs