Assessment Year | 2009 |
---|---|
Principal Product | Metal Light Gauge Rolling |
NAICS | 331318: Other Aluminum Rolling, Drawing, and Extruding |
SIC | 3355: Aluminum Rolling and Drawing, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 113 |
Plant Area |
99,000
ft2
|
Annual Production | 27,000
ton
|
Production Hrs. Annual | 8,430
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,916,740 | 16,962,305 |
kWh
|
$0.11 |
Natural Gas | $1,458,268 | 102,695 |
MMBtu
|
$14.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $197,803 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7243: Improve air circulation with destratification fans / other methods | $89,460 | $41,150 | - |
$89,460
-
MMBtu
|
|
02 | 2.2437: Recover waste heat from equipment | $31,002 | $5,550 | - |
$31,002
-
MMBtu
|
|
03 | 2.2437: Recover waste heat from equipment | $21,300 | $575 | - |
$21,300
-
MMBtu
|
|
04 | 2.4239: Eliminate or reduce compressed air usage | $12,400 | $950 |
$12,400
110,000
kWh
|
- | |
05 | 2.2611: Moderate cooling tower outlet temperature | $6,452 | - |
$6,452
57,093
kWh
|
- | |
06 | 2.4131: Size electric motors for peak operating efficiency | $37,189 | $70,000 |
$37,189
329,107
kWh
|
- | |
TOTAL RECOMMENDED | $197,803 | $118,225 |
$56,041
496,200
kWh
|
$141,762
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs