ITAC Assessment: DL0043
ITAC logo
ITAC Assessment: DL0043
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product plumbing fixtures
NAICS 332913: Plumbing Fixture Fitting and Trim Manufacturing
SIC 3432: Plumbing Fixture Fittings and Trim
Sales Range $10
M
to 50
M
# of Employees 114
Plant Area 65,000
ft2
Annual Production 96,000
pieces
Production Hrs. Annual 3,120
hrs
Location (State) Delaware

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $105,827 663,920
kWh
Natural Gas $38 2,556
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $21,444 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,724

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7243: Improve air circulation with destratification fans / other methods $9,690 $18,300 - - $9,690
-
MMBtu
02 2.7221: Lower temperature during the winter season and vice-versa $3,192 - - - $3,192
-
MMBtu
03 2.7232: Replace existing hvac unit with high efficiency model $5,472 $3,500 - - $5,472
-
MMBtu
04 2.2437: Recover waste heat from equipment $600 $950 - - $600
-
MMBtu
05 2.7142: Utilize higher efficiency lamps and/or ballasts $960 $2,000 $960
6,440
kWh
- -
06 2.6211: Conserve energy by efficient use of vending machines $470 $510 $470
3,150
kWh
- -
07 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,060 - - $1,060
-
kW-mo/yr
-
TOTAL RECOMMENDED $21,444 $25,260 $1,430
9,590
kWh
$1,060
-
kW-mo/yr
$18,954
-
MMBtu
TOTAL IMPLEMENTED $9,724 $3,500 - $1,060
-
kW-mo/yr
$8,664
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs