ITAC Assessment: DL0024
ITAC logo
ITAC Assessment: DL0024
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Pepsi, Mountain Dew, Diet versions, Pepsi One, Jazz, Sierra Mist, Pepsi
NAICS 312111: Soft Drink Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $100
M
to 500
M
# of Employees 400
Plant Area 600,000
ft2
Annual Production 25,000,000
pieces
Production Hrs. Annual 6,656
hrs
Location (State) Maryland

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $882,895 10,041,460
kWh
Electricity Demand $4,398 1,904
kW-mo/yr
Electricity Fees $48,317 -
Natural Gas $503,812 55,954
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $359,032 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $69,865

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2437: Recover waste heat from equipment $160,536 $150,000 - $160,536
-
MMBtu
02 2.1224: Replace boiler $116,210 $102,000 - $116,210
-
MMBtu
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $21,865 $11,000 $21,865
227,760
kWh
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $12,421 $3,877 $12,421
103,512
kWh
-
05 2.2135: Repair and eliminate steam leaks $10,800 $1,200 - $10,800
-
MMBtu
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $37,200 $112,000 $37,200
310,000
kWh
-
TOTAL RECOMMENDED $359,032 $380,077 $71,486
641,272
kWh
$287,546
-
MMBtu
TOTAL IMPLEMENTED $69,865 $124,200 $59,065
537,760
kWh
$10,800
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs