ITAC Assessment: DL0014
ITAC logo
ITAC Assessment: DL0014
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Flopack Cushioning, Recycled Polystyrene
NAICS 326140: Polystyrene Foam Product Manufacturing
SIC 3086: Plastics Foam Products
Sales Range $10
M
to 50
M
# of Employees 35
Plant Area 35,000
ft2
Annual Production 1,300
ton
Production Hrs. Annual 6,240
hrs
Location (State) Delaware

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $240,256 1,453,920
kWh
Natural Gas $200,810 16,520
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $21,424 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,600

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.6218: Turn off equipment when not in use $3,600 - - $3,600
-
MMBtu
02 2.7491: Insulate glazing, walls, ceilings, and roofs $470 $635 - $470
-
MMBtu
03 2.2136: Install / repair insulation on steam lines $2,173 $4,200 - $2,173
-
MMBtu
04 2.7142: Utilize higher efficiency lamps and/or ballasts $5,481 $12,133 $5,481
49,824
kWh
-
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $5,500 $15,000 $5,500
50,000
kWh
-
06 2.2414: Use waste heat from hot flue gases to preheat $4,200 $20,000 - $4,200
-
MMBtu
TOTAL RECOMMENDED $21,424 $51,968 $10,981
99,824
kWh
$10,443
-
MMBtu
TOTAL IMPLEMENTED $3,600 - - $3,600
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs