Assessment Year | 2008 |
---|---|
Principal Product | noise control and thermal applications |
NAICS | 326150: Urethane and Other Foam Product (except Polystyrene) Manufacturing |
SIC | 3086: Plastics Foam Products |
Sales Range | $10 M to 50M |
# of Employees | 110 |
Plant Area |
76,000
ft2
|
Annual Production | 1,500
thousand feet
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Delaware |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $57,925 | 913,000 |
kWh
|
$0.063 |
Electricity Demand | $39,575 | 199 |
kW-mo/yr
|
$198.87 |
Electricity Fees | $4,462 | - |
|
- |
Natural Gas | $33,705 | 2,472 |
MMBtu
|
$13.63 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $67,003 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $27,593 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $27,593 | $26,675 |
$27,047
245,880
kWh
|
$546
-
kW-mo/yr
|
- | - | |
02 | 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air | $19,600 | $23,900 | - | - |
$19,600
-
MMBtu
|
- | |
03 | 2.2531: Re-size charging openings or add movable cover or door | $5,988 | $146 | - | - |
$5,988
-
MMBtu
|
- | |
04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $6,766 | $16,500 | - | - |
$6,766
-
MMBtu
|
- | |
05 | 2.8114: Change rate schedules or other changes in utility service | $3,154 | - | - | - | - | $3,154 | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,902 | $11,000 |
$3,902
34,968
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $67,003 | $78,221 |
$30,949
280,848
kWh
|
$546
-
kW-mo/yr
|
$32,354
-
MMBtu
|
$3,154 | ||
TOTAL IMPLEMENTED | $27,593 | $26,675 |
$27,047
245,880
kWh
|
$546
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs