| Assessment Year | 2022 |
|---|---|
| Principal Product | Rigid PVC cubes and pellets |
| NAICS | 325991: Custom Compounding of Purchased Resins |
| SIC | 3087: Custom Compounding of Purchased Plastics Resins |
| Sales Range | $100 M to 500M |
| # of Employees | 65 |
| Plant Area |
300,000
ft2
|
| Annual Production | 100,000,000
lb
|
| Production Hrs. Annual | 8,000
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $1,401,668 | 20,246,711 |
kWh
|
$0.069 | |
| Electricity Demand | $1,221,173 | 125,142 |
kW-mo/yr
|
$9.76 | |
| Natural Gas | $330,596 | 57,248 |
MMBtu
|
$5.77 | |
| Waste Disposal Costs | |||||
| Water Usage | $260,759 | 24,586 |
Tgal
|
$10.61 | |
| TOTAL YEARLY COSTS | $3,214,196 | ||||
| RECOMMENDED SAVINGS* | $245,171 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,655 | $2,019 |
$6,655
96,445
kWh
|
- | - | - | |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $17,007 | $17,900 |
$17,007
246,478
kWh
|
- | - | - | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $37,427 | $1,156 |
$37,427
542,426
kWh
|
- | - | - | |
| 04 | 2.4314: Use synthetic lubricant | $18,816 | $9,059 |
$18,816
272,699
kWh
|
- | - | - | |
| 05 | 2.1223: Install smaller boiler (increase high fire duty cycle) | $23,398 | $56,000 | - | - |
$23,398
-
MMBtu
|
- | |
| 06 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $70,112 | $8,000 |
$(-1,478.0)
(-21,420)
kWh
|
$(-409.9)
-
kW-mo/yr
|
- | $72,000 | |
| 07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,449 | $25,995 |
$8,449
122,450
kWh
|
- | - | - | |
| 08 | 2.9114: Use solar heat to make electricty | $63,307 | $41,871 |
$63,307
917,489
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $245,171 | $162,000 |
$150,183
2,176,567
kWh
|
$(-409.9)
-
kW-mo/yr
|
$23,398
-
MMBtu
|
$72,000 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs