| Assessment Year | 2022 |
|---|---|
| Principal Product | Commercial and Military Aircraft Power Generation |
| NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 130 |
| Plant Area |
44,000
ft2
|
| Annual Production | 13,000
units
|
| Production Hrs. Annual | 3,000
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $67,614 | 1,432,500 |
kWh
|
$0.047 |
| Electricity Demand | $56,540 | 5,040 |
kW-mo/yr
|
$11.22 |
| Electricity Fees | $20,863 | - |
|
- |
| TOTAL YEARLY COSTS | $145,018 | |||
| RECOMMENDED SAVINGS* | $1,085,605 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,085,605 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.652: Replace existing equipment with more suitable substitutes | $30,000 | $70,084 | - | - | - | - | $30,000 | |
| 02 | 4.651: Install back-up equipment | $32,054 | $93,000 | - | - | $32,054 | - | - | |
| 03 | 2.3141: Use battery storage for demand control | $18,089 | $25,885 |
$18,089
383,250
kWh
|
- | - | - | - | |
| 04 | 4.454: Modify startup/shutdown times | $2,380 | $100,000 |
$2,380
50,430
kWh
|
- | - | - | - | |
| 05 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $1,965 | $510 |
$191
4,053
kWh
|
$1,774
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $899 | - |
$899
19,049
kWh
|
- | - | - | - | |
| 07 | 4.611: Begin a practice of predictive / preventative maintenance | $1,000,000 | $122,000 | - | - | - | $1,000,000 | - | |
| 08 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $217 | $86 |
$217
4,596
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $1,085,605 | $411,565 |
$21,777
461,377
kWh
|
$1,774
-
kW-mo/yr
|
$32,054 | $1,000,000 | $30,000 | ||
| TOTAL IMPLEMENTED | $1,085,605 | $411,565 |
$21,777
461,377
kWh
|
$1,774
-
kW-mo/yr
|
$32,054 | $1,000,000 | $30,000 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs