Assessment Year | 2022 |
---|---|
Principal Product | Plastic biomedical components |
NAICS | 326122: Plastics Pipe and Pipe Fitting Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 50 |
Plant Area |
13,120
ft2
|
Annual Production | 120,000,000
pieces
|
Production Hrs. Annual | 8,592
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $62,489 | 769,216 |
kWh
|
$0.081 |
Electricity Demand | $17,306 | 1,051 |
kW-mo/yr
|
$16.47 |
Electricity Fees | $3,861 | - |
|
- |
Natural Gas | $6,220 | 647 |
MMBtu
|
$9.61 |
TOTAL YEARLY COSTS | $89,876 | |||
RECOMMENDED SAVINGS* | $304,985 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $26,159 | $136,687 |
$16,642
208,291
kWh
|
$1,706
-
kW-mo/yr
|
- | $7,811 | - | |
02 | 2.2437: Recover waste heat from equipment | $881 | $2,407 | - | - |
$881
-
MMBtu
|
- | - | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $2,175 | $7,076 |
$2,175
18,633
kWh
|
- | - | - | - | |
04 | 2.7144: Install spectral reflectors / delamp | $1,847 | $9,768 |
$1,595
16,044
kWh
|
$252
-
kW-mo/yr
|
- | - | - | |
05 | 2.3192: Use fossil fuel powered generator during peak demand periods | $210,000 | $58,000 | - | - | - | - | $210,000 | |
06 | 2.3513: Consider power loss as well as initial loads and load growth in down-sizing transformers | $60,192 | $4,219 |
$132
1,657
kWh
|
- | - | - | $60,060 | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,731 | $3,276 |
$3,248
31,511
kWh
|
$483
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $304,985 | $221,433 |
$23,792
276,136
kWh
|
$2,441
-
kW-mo/yr
|
$881
-
MMBtu
|
$7,811 | $270,060 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs