| Assessment Year | 2021 |
|---|---|
| Principal Product | Billboards, canvas prints, business signage |
| NAICS | 323111: Commercial Printing (except Screen and Books) |
| SIC | 2759: Commercial Printing, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 500 |
| Plant Area |
275,000
ft2
|
| Annual Production | 193,500,000
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $299,298 | 6,212,847 |
kWh
|
$0.048 | |
| Electricity Demand | $125,598 | 10,853 |
kW-mo/yr
|
$11.57 | |
| Electricity Fees | $5,436 | - |
|
- | |
| Natural Gas | $121,663 | 34,009 |
MMBtu
|
$3.58 | |
| Waste Disposal Costs | |||||
| Water Usage | $9,576 | 1,030 |
Tgal
|
$9.30 | |
| TOTAL YEARLY COSTS | $561,571 | ||||
| RECOMMENDED SAVINGS* | $50,377 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $6,421 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $14,076 | $28,500 | - | - |
$14,076
-
MMBtu
|
|
| 02 | 2.9114: Use solar heat to make electricty | $28,176 | $298,655 |
$15,675
327,238
kWh
|
$12,501
-
kW-mo/yr
|
- | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $372 | $617 |
$276
5,767
kWh
|
$96
-
kW-mo/yr
|
- | |
| 04 | 2.3132: Recharge batteries on during off-peak demand periods | $1,332 | - | - |
$1,332
-
kW-mo/yr
|
- | |
| 05 | 2.7135: Install occupancy sensors | $6,421 | $667 |
$6,421
133,329
kWh
|
- | - | |
| TOTAL RECOMMENDED | $50,377 | $328,439 |
$22,372
466,334
kWh
|
$13,929
-
kW-mo/yr
|
$14,076
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $6,421 | $667 |
$6,421
133,329
kWh
|
- | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs