Assessment Year | 2016 |
---|---|
Principal Product | Packaged meal kits |
NAICS | 311991: Perishable Prepared Food Manufacturing |
SIC | 2099: Food Preparations, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
50,940
ft2
|
Annual Production | 624,000
units
|
Production Hrs. Annual | 5,708
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $39,991 | 985,440 |
kWh
|
$0.041 |
Electricity Demand | $50,043 | 2,268 |
kW-mo/yr
|
$22.06 |
Electricity Fees | $564 | - |
|
- |
Natural Gas | $14,826 | 2,650 |
MMBtu
|
$5.59 |
TOTAL YEARLY COSTS | $105,424 | |||
RECOMMENDED SAVINGS* | $25,450 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2626: Avoid frost formation on evaporators | $8,830 | $19,500 |
$2,870
71,300
kWh
|
$5,960
-
kW-mo/yr
|
- | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $3,940 | $5,530 |
$2,120
52,500
kWh
|
$1,820
-
kW-mo/yr
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,340 | $15,060 |
$4,660
115,600
kWh
|
$5,740
-
kW-mo/yr
|
$170 | - | $(-1,230.0) | |
04 | 2.8121: Apply for tax-free status for energy purchases | $3,340 | $500 | - | - | - | $3,340 | - | |
TOTAL RECOMMENDED | $25,450 | $40,590 |
$9,650
239,400
kWh
|
$13,520
-
kW-mo/yr
|
$170 | $3,340 | $(-1,230.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs