ITAC Assessment: CO0736
ITAC logo
ITAC Assessment: CO0736
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Packaged meal kits
NAICS 311991: Perishable Prepared Food Manufacturing
SIC 2099: Food Preparations, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 50,940
ft2
Annual Production 624,000
units
Production Hrs. Annual 5,708
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $39,991 985,440
kWh
Electricity Demand $50,043 2,268
kW-mo/yr
Electricity Fees $564 -
Natural Gas $14,826 2,650
MMBtu
TOTAL YEARLY COSTS $105,424
RECOMMENDED SAVINGS* $25,450 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.2626: Avoid frost formation on evaporators $8,830 $19,500 $2,870
71,300
kWh
$5,960
-
kW-mo/yr
- - -
02 2.4133: Use most efficient type of electric motors $3,940 $5,530 $2,120
52,500
kWh
$1,820
-
kW-mo/yr
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $9,340 $15,060 $4,660
115,600
kWh
$5,740
-
kW-mo/yr
$170 - $(-1,230.0)
04 2.8121: Apply for tax-free status for energy purchases $3,340 $500 - - - $3,340 -
TOTAL RECOMMENDED $25,450 $40,590 $9,650
239,400
kWh
$13,520
-
kW-mo/yr
$170 $3,340 $(-1,230.0)
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs