Assessment Year | 2015 |
---|---|
Principal Product | Perishable Foods |
NAICS | 311991: Perishable Prepared Food Manufacturing |
SIC | 2099: Food Preparations, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 65 |
Plant Area |
30,500
ft2
|
Annual Production | 50,000
pieces
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $33,495 | 767,760 |
kWh
|
$0.044 |
Electricity Demand | $39,191 | 1,887 |
kW-mo/yr
|
$20.77 |
Electricity Fees | $586 | - |
|
- |
Natural Gas | $50,293 | 7,061 |
MMBtu
|
$7.12 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,770 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,170 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,310 | $1,000 |
$760
19,000
kWh
|
$550
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.2623: Minimize condenser cooling water temperature | $960 | $630 |
$560
14,000
kWh
|
$400
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $840 | $1,110 |
$490
12,100
kWh
|
$350
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.2626: Avoid frost formation on evaporators | $380 | $1,960 |
$380
9,600
kWh
|
- | - | - | - | - | |
05 | 2.4133: Use most efficient type of electric motors | $260 | $590 |
$150
3,800
kWh
|
$110
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.8121: Apply for tax-free status for energy purchases | $4,560 | $500 | - | - | - | - | $4,560 | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,300 | $10,780 |
$2,270
56,700
kWh
|
$1,930
-
kW-mo/yr
|
- | $160 | - | $(-60.0) | |
08 | 2.9111: Use solar heat to heat make-up air | $1,160 | $8,080 | - | - |
$1,160
-
MMBtu
|
- | - | - | |
TOTAL RECOMMENDED | $13,770 | $24,650 |
$4,610
115,200
kWh
|
$3,340
-
kW-mo/yr
|
$1,160
-
MMBtu
|
$160 | $4,560 | $(-60.0) | ||
TOTAL IMPLEMENTED | $10,170 | $12,280 |
$3,030
75,700
kWh
|
$2,480
-
kW-mo/yr
|
- | $160 | $4,560 | $(-60.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs