Assessment Year | 2015 |
---|---|
Principal Product | Manufactured Stone Veneers |
NAICS | 327991: Cut Stone and Stone Product Manufacturing |
SIC | 3281: Cut Stone and Stone Products |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
72,000
ft2
|
Annual Production | 4,000,000
pieces
|
Production Hrs. Annual | 3,393
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $44,995 | 960,095 |
kWh
|
$0.047 |
Electricity Demand | $55,366 | 2,877 |
kW-mo/yr
|
$19.24 |
Electricity Fees | $4,762 | - |
|
- |
Natural Gas | $38,208 | 5,407 |
MMBtu
|
$7.07 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,430 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,170 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,880 | $460 |
$1,460
33,800
kWh
|
$2,420
-
kW-mo/yr
|
- | - | |
02 | 2.2437: Recover waste heat from equipment | $2,260 | $8,620 | - | - |
$2,260
-
MMBtu
|
- | |
03 | 2.8121: Apply for tax-free status for energy purchases | $5,290 | $500 | - | - | - | $5,290 | |
TOTAL RECOMMENDED | $11,430 | $9,580 |
$1,460
33,800
kWh
|
$2,420
-
kW-mo/yr
|
$2,260
-
MMBtu
|
$5,290 | ||
TOTAL IMPLEMENTED | $9,170 | $960 |
$1,460
33,800
kWh
|
$2,420
-
kW-mo/yr
|
- | $5,290 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs