ITAC Assessment: CO0694
ITAC logo
ITAC Assessment: CO0694
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Can Press and Printing Machines
NAICS 333517: Machine Tool Manufacturing
SIC 3542: Machine Tools, Metal Forming Types
Sales Range greater than $500
M
# of Employees 210
Plant Area 136,250
ft2
Annual Production 175
pieces
Production Hrs. Annual 5,616
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $92,290 2,084,000
kWh
Electricity Demand $114,882 5,327
kW-mo/yr
Electricity Fees $618 -
Natural Gas $48,334 7,359
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $23,770 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,630 $470 $5,260
114,400
kWh
$3,370
-
kW-mo/yr
- - -
02 2.8121: Apply for tax-free status for energy purchases $7,790 $1,500 - - - $7,790 -
03 2.7134: Use photocell controls $3,870 $7,930 $3,580
77,900
kWh
- $90 - $200
04 2.7142: Utilize higher efficiency lamps and/or ballasts $3,480 $9,250 $1,260
27,300
kWh
$1,750
-
kW-mo/yr
$70 - $400
TOTAL RECOMMENDED $23,770 $19,150 $10,100
219,600
kWh
$5,120
-
kW-mo/yr
$160 $7,790 $600
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs