ITAC Assessment: CO0692
ITAC logo
ITAC Assessment: CO0692
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Pharmaceuticals
NAICS 325412: Pharmaceutical Preparation Manufacturing
SIC 2834: Pharmaceutical Preparations
Sales Range $100
M
to 500
M
# of Employees 325
Plant Area 27,000
ft2
Annual Production 20,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) New Mexico

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $703,693 11,865,600
kWh
Electricity Demand $244,854 22,203
kW-mo/yr
Electricity Fees $91,219 -
Natural Gas $214,451 37,920
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $49,990 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $47,210

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4133: Use most efficient type of electric motors $2,780 $10,910 $2,160
33,100
kWh
$620
-
kW-mo/yr
- - -
02 2.8121: Apply for tax-free status for energy purchases $39,420 $1,250 - - - $39,420 -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $7,790 $21,020 $4,580
68,300
kWh
$1,640
-
kW-mo/yr
$130 - $1,440
TOTAL RECOMMENDED $49,990 $33,180 $6,740
101,400
kWh
$2,260
-
kW-mo/yr
$130 $39,420 $1,440
TOTAL IMPLEMENTED $47,210 $22,270 $4,580
68,300
kWh
$1,640
-
kW-mo/yr
$130 $39,420 $1,440
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs