ITAC Assessment: CO0691
ITAC logo
ITAC Assessment: CO0691
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Tortillas and Prepared Foods
NAICS 311830: Tortilla Manufacturing
SIC 2099: Food Preparations, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 49,000
ft2
Annual Production 240,000
pieces
Production Hrs. Annual 2,600
hrs
Location (State) New Mexico

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $151,298 2,452,080
kWh
Electricity Demand $12,661 6,710
kW-mo/yr
Electricity Fees $101,160 -
Natural Gas $67,747 11,021
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,110 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,180

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,050 $440 $1,300
17,400
kWh
$750
-
kW-mo/yr
-
02 2.8121: Apply for tax-free status for energy purchases $9,130 $1,250 - - $9,130
03 2.4133: Use most efficient type of electric motors $4,930 $10,510 $3,780
51,000
kWh
$1,150
-
kW-mo/yr
-
TOTAL RECOMMENDED $16,110 $12,200 $5,080
68,400
kWh
$1,900
-
kW-mo/yr
$9,130
TOTAL IMPLEMENTED $11,180 $1,690 $1,300
17,400
kWh
$750
-
kW-mo/yr
$9,130
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs