Assessment Year | 2007 |
---|---|
Principal Product | Silicone and metal products |
NAICS | 339112: Surgical and Medical Instrument Manufacturing |
SIC | 3841: Surgical and Medical Instruments and Apparatus |
Sales Range | $5 M to 10M |
# of Employees | 55 |
Plant Area |
30,000
ft2
|
Annual Production | 96,000
pieces
|
Production Hrs. Annual | 2,730
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $136,340 | 1,084,320 |
kWh
|
$0.13 |
Electricity Demand | $39,006 | 4,224 |
kW-mo/yr
|
$9.23 |
Electricity Fees | $8,085 | - |
|
- |
Natural Gas | $24,816 | 1,616 |
MMBtu
|
$15.36 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $27,151 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,940 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $13,848 | $117,000 |
$13,268
105,300
kWh
|
$7,476
-
kW-mo/yr
|
$(-6,896.0)
-
MMBtu
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,363 | $50,282 |
$4,813
38,200
kWh
|
$1,550
-
kW-mo/yr
|
- | |
03 | 2.7221: Lower temperature during the winter season and vice-versa | $6,297 | $1,184 | - | - |
$6,297
-
MMBtu
|
|
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $643 | $460 |
$643
5,100
kWh
|
- | - | |
TOTAL RECOMMENDED | $27,151 | $168,926 |
$18,724
148,600
kWh
|
$9,026
-
kW-mo/yr
|
$(-599.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $6,940 | $1,644 |
$643
5,100
kWh
|
- |
$6,297
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs