Assessment Year | 2014 |
---|---|
Principal Product | Toner Cartridges |
NAICS | 325992: Photographic Film, Paper, Plate, and Chemical Manufacturing |
SIC | 3861: Photographic Equipment and Supplies |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
90,000
ft2
|
Annual Production | 300,000
pieces
|
Production Hrs. Annual | 2,223
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $25,311 | 599,853 |
kWh
|
$0.042 |
Electricity Demand | $61,629 | 2,963 |
kW-mo/yr
|
$20.80 |
Electricity Fees | $2,416 | - |
|
- |
Natural Gas | $26,418 | 3,584 |
MMBtu
|
$7.37 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,720 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,850 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4239: Eliminate or reduce compressed air usage | $1,730 | $1,460 |
$480
10,900
kWh
|
$1,250
-
kW-mo/yr
|
- | - | - | |
02 | 2.6218: Turn off equipment when not in use | $1,180 | - |
$1,180
27,100
kWh
|
- | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $940 | $370 |
$260
6,000
kWh
|
$680
-
kW-mo/yr
|
- | - | - | |
04 | 2.7243: Improve air circulation with destratification fans / other methods | $5,790 | $28,490 |
$(-240.0)
(-5,500)
kWh
|
$(-170.0)
-
kW-mo/yr
|
$6,200
-
MMBtu
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,080 | $5,800 |
$1,370
31,600
kWh
|
$570
-
kW-mo/yr
|
- | $50 | $90 | |
TOTAL RECOMMENDED | $11,720 | $36,120 |
$3,050
70,100
kWh
|
$2,330
-
kW-mo/yr
|
$6,200
-
MMBtu
|
$50 | $90 | ||
TOTAL IMPLEMENTED | $3,850 | $1,830 |
$1,920
44,000
kWh
|
$1,930
-
kW-mo/yr
|
- | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs