ITAC Assessment: CO0687
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Oil & Gas Well Optimization Equipment
NAICS 333911: Pump and Pumping Equipment Manufacturing
SIC 3561: Pumps and Pumping Equipment
Sales Range $100
M
to 500
M
# of Employees 390
Plant Area 45,700
ft2
Annual Production 420,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $69,335 1,205,760
kWh
Electricity Demand $43,151 2,400
kW-mo/yr
Electricity Fees $756 -
Natural Gas $4,454 576
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,460 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,320

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,210 $2,210 $3,770
62,100
kWh
$1,440
-
kW-mo/yr
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $3,220 $6,060 $2,090
34,400
kWh
$980
-
kW-mo/yr
$60 - $90
03 2.8121: Apply for tax-free status for energy purchases $3,110 $1,500 - - - $3,110 -
04 2.7135: Install occupancy sensors $1,920 $2,480 $1,800
29,700
kWh
- $30 - $90
TOTAL RECOMMENDED $13,460 $12,250 $7,660
126,200
kWh
$2,420
-
kW-mo/yr
$90 $3,110 $180
TOTAL IMPLEMENTED $8,320 $3,710 $3,770
62,100
kWh
$1,440
-
kW-mo/yr
- $3,110 -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs