ITAC Assessment: CO0679
ITAC logo
ITAC Assessment: CO0679
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Safety equipment
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 90,000
ft2
Annual Production 500,000
pieces
Production Hrs. Annual 2,730
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $61,997 1,590,720
kWh
Electricity Demand $74,059 3,652
kW-mo/yr
Electricity Fees $1,824 -
Natural Gas $4,732 539
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $21,850 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,230

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,910 $360 $2,330
57,500
kWh
$1,580
-
kW-mo/yr
- -
02 2.7231: Use radiant heater for spot heating $1,740 $1,320 $550
13,700
kWh
$600
-
kW-mo/yr
$60 $530
03 2.7229: Air condition only space necessary $9,040 $500 $4,810
119,000
kWh
$4,230
-
kW-mo/yr
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $6,450 $15,070 $1,930
44,200
kWh
$4,460
-
kW-mo/yr
$70 $(-10.0)
05 2.7142: Utilize higher efficiency lamps and/or ballasts $710 $4,160 $540
12,800
kWh
- $100 $70
TOTAL RECOMMENDED $21,850 $21,410 $10,160
247,200
kWh
$10,870
-
kW-mo/yr
$230 $590
TOTAL IMPLEMENTED $17,230 $16,890 $7,290
176,900
kWh
$9,290
-
kW-mo/yr
$130 $520
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs