Assessment Year | 2013 |
---|---|
Principal Product | Industrial cleaning equipment |
NAICS | 333318: Other Commercial and Service Industry Machinery Manufacturing |
SIC | 3589: Service Industry Machinery, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 450 |
Plant Area |
191,000
ft2
|
Annual Production | 7,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $123,297 | 3,325,301 |
kWh
|
$0.037 |
Electricity Demand | $228,263 | 11,268 |
kW-mo/yr
|
$20.26 |
Electricity Fees | $4,799 | - |
|
- |
Natural Gas | $106,216 | 22,178 |
MMBtu
|
$4.79 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $46,240 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $46,240 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $11,280 | $45,000 |
$5,590
139,800
kWh
|
$5,690
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,280 | $2,040 |
$2,120
53,100
kWh
|
$2,160
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $25,450 | $48,290 |
$14,690
367,800
kWh
|
$9,880
-
kW-mo/yr
|
- | $600 | - | $280 | |
04 | 2.8114: Change rate schedules or other changes in utility service | $3,280 | $500 |
$(-5,090.0)
-
kWh
|
$7,510
-
kW-mo/yr
|
$860 | - | - | - | |
05 | 2.8121: Apply for tax-free status for energy purchases | $1,950 | $500 | - | - | - | - | $1,950 | - | |
TOTAL RECOMMENDED | $46,240 | $96,330 |
$17,310
560,700
kWh
|
$25,240
-
kW-mo/yr
|
$860 | $600 | $1,950 | $280 | ||
TOTAL IMPLEMENTED | $46,240 | $96,330 |
$17,310
560,700
kWh
|
$25,240
-
kW-mo/yr
|
$860 | $600 | $1,950 | $280 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs