ITAC Assessment: CO0667
ITAC logo
ITAC Assessment: CO0667
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Pumps and compressors
NAICS 333911: Pump and Pumping Equipment Manufacturing
SIC 3561: Pumps and Pumping Equipment
Sales Range $100
M
to 500
M
# of Employees 429
Plant Area 191,000
ft2
Annual Production 4,200
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $289,934 7,588,875
kWh
Electricity Demand $459,742 25,945
kW-mo/yr
Electricity Fees $15,758 -
Natural Gas $44,384 6,984
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $50,100 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $47,980

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.3191: Use demand controller or load shedder $21,220 $50,000 - $21,220
-
kW-mo/yr
- - -
02 2.4133: Use most efficient type of electric motors $2,950 $17,590 $1,760
49,800
kWh
$1,190
-
kW-mo/yr
- - -
03 2.4239: Eliminate or reduce compressed air usage $1,460 $11,450 $720
20,300
kWh
$740
-
kW-mo/yr
- - -
04 2.7226: Use computer programs to optimize hvac performance $13,790 $35,250 $(-70.0)
(-1,900)
kWh
- $13,860
-
MMBtu
- -
05 2.7226: Use computer programs to optimize hvac performance $2,370 $4,500 $960
27,100
kWh
- $1,410
-
MMBtu
- -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,120 $15,820 $1,200
33,800
kWh
$920
-
kW-mo/yr
- - -
07 2.7132: Install timers on light switches in little used areas $6,190 $15,000 $5,330
150,500
kWh
- - $320 $540
TOTAL RECOMMENDED $50,100 $149,610 $9,900
279,600
kWh
$24,070
-
kW-mo/yr
$15,270
-
MMBtu
$320 $540
TOTAL IMPLEMENTED $47,980 $133,790 $8,700
245,800
kWh
$23,150
-
kW-mo/yr
$15,270
-
MMBtu
$320 $540
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs