| Assessment Year | 2012 |
|---|---|
| Principal Product | Erosion and sediment control products |
| NAICS | 321999: All Other Miscellaneous Wood Product Manufacturing |
| SIC | 2429: Special Product Sawmills, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 125 |
| Plant Area |
81,000
ft2
|
| Annual Production | 6,240
ton
|
| Production Hrs. Annual | 5,512
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $347,147 | 3,407,420 |
kWh
|
$0.10 |
| Electricity Demand | $94,999 | 14,151 |
kW-mo/yr
|
$6.71 |
| Electricity Fees | $5,349 | - |
|
- |
| Natural Gas | $9,724 | 1,601 |
MMBtu
|
$6.07 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $88,560 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,710 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $25,240 | $155,860 |
$18,180
221,800
kWh
|
$7,060
-
kW-mo/yr
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,710 | $1,000 |
$4,590
60,100
kWh
|
$1,120
-
kW-mo/yr
|
- | |
| 03 | 2.4239: Eliminate or reduce compressed air usage | $3,090 | $430 |
$2,490
32,600
kWh
|
$600
-
kW-mo/yr
|
- | |
| 04 | 2.3212: Optimize plant power factor | $30,160 | $56,610 | - |
$30,160
-
kW-mo/yr
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,630 | $32,970 |
$11,240
140,600
kWh
|
$3,290
-
kW-mo/yr
|
$210 | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,730 | $13,270 |
$7,110
90,500
kWh
|
$2,350
-
kW-mo/yr
|
$160 | |
| TOTAL RECOMMENDED | $88,560 | $260,140 |
$43,610
545,600
kWh
|
$44,580
-
kW-mo/yr
|
$370 | ||
| TOTAL IMPLEMENTED | $5,710 | $1,000 |
$4,590
60,100
kWh
|
$1,120
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs