ITAC Assessment: CO0662
ITAC logo
ITAC Assessment: CO0662
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Creosote Treated Railroad Ties
NAICS 321114: Wood Preservation
SIC 2491: Wood Preserving
Sales Range $10
M
to 50
M
# of Employees 32
Plant Area 21,300
ft2
Annual Production 2,400,000
units
Production Hrs. Annual 7,176
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $96,090 2,584,610
kWh
Electricity Demand $108,890 6,487
kW-mo/yr
Electricity Fees $3,832 -
Natural Gas $275,603 42,247
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $35,010 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,420

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,990 $850 $2,390
68,600
kWh
$1,600
-
kW-mo/yr
- - - -
02 2.2135: Repair and eliminate steam leaks $3,070 $430 - - $3,070
-
MMBtu
- - -
03 2.4239: Eliminate or reduce compressed air usage $1,930 $3,460 $1,060
30,500
kWh
$870
-
kW-mo/yr
- - - -
04 2.8121: Apply for tax-free status for energy purchases $13,030 $500 - - - - $13,030 -
05 2.9114: Use solar heat to make electricty $7,350 $33,500 - - $7,350
-
MMBtu
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $4,330 $8,900 $1,750
50,300
kWh
$1,490
-
kW-mo/yr
- $440 - $650
07 2.6231: Utilize controls to operate equipment only when needed $1,310 $1,580 $1,010
33,000
kWh
$300
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $35,010 $49,220 $6,210
182,400
kWh
$4,260
-
kW-mo/yr
$10,420
-
MMBtu
$440 $13,030 $650
TOTAL IMPLEMENTED $24,420 $10,680 $4,140
118,900
kWh
$3,090
-
kW-mo/yr
$3,070
-
MMBtu
$440 $13,030 $650
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs