ITAC Assessment: CO0658
ITAC logo
ITAC Assessment: CO0658
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Processed meat products
NAICS 311611: Animal (except Poultry) Slaughtering
SIC 2011: Meat Packing Plants
Sales Range less than $500
k
# of Employees 900
Plant Area 172,000
ft2
Annual Production 1
units
Production Hrs. Annual 3,120
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $315,558 5,149,050
kWh
Electricity Demand $237,064 11,952
kW-mo/yr
Electricity Fees $1,742 -
Natural Gas $32,319 3,778
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $30,840 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $15,090

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7221: Lower temperature during the winter season and vice-versa $9,430 $850 $12,180
191,900
kWh
$520
-
kW-mo/yr
$(-3,270.0)
-
MMBtu
- -
02 2.7135: Install occupancy sensors $7,240 $29,960 $6,680
105,300
kWh
- - $100 $460
03 2.7134: Use photocell controls $6,600 $4,680 $3,410
53,700
kWh
$2,920
-
kW-mo/yr
- $50 $220
04 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle $5,660 $550 $480
7,500
kWh
$530
-
kW-mo/yr
$4,650
-
MMBtu
- -
05 2.7221: Lower temperature during the winter season and vice-versa $1,460 $9,100 $1,000
15,700
kWh
$460
-
kW-mo/yr
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $450 $2,400 $120
1,900
kWh
$190
-
kW-mo/yr
- $40 $100
TOTAL RECOMMENDED $30,840 $47,540 $23,870
376,000
kWh
$4,620
-
kW-mo/yr
$1,380
-
MMBtu
$190 $780
TOTAL IMPLEMENTED $15,090 $1,400 $12,660
199,400
kWh
$1,050
-
kW-mo/yr
$1,380
-
MMBtu
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs