Assessment Year | 2011 |
---|---|
Principal Product | Wood boards |
NAICS | 321113: Sawmills |
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $1 M to 5M |
# of Employees | 41 |
Plant Area |
15,000
ft2
|
Annual Production | 3,000,000
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $82,505 | 1,371,815 |
kWh
|
$0.060 |
Electricity Demand | $85,385 | 7,813 |
kW-mo/yr
|
$10.93 |
Electricity Fees | $5,088 | - |
|
- |
Natural Gas | $1,470 | 161 |
MMBtu
|
$9.13 |
Fuel Oil #2 | $13,389 | 612 |
MMBtu
|
$21.88 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $31,190 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,090 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1336: Install equipment to utilize waste fuel | $11,990 | $34,320 | - | - |
$(-1,400.0)
-
MMBtu
|
$13,390
-
MMBtu
|
|
02 | 2.5195: Change product design to reduce energy requirements | $7,570 | $13,550 |
$3,230
54,300
kWh
|
$4,340
-
kW-mo/yr
|
- | - | |
03 | 2.9111: Use solar heat to heat make-up air | $7,530 | $35,420 | - | - | - |
$7,530
-
MMBtu
|
|
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,100 | $870 |
$2,880
48,400
kWh
|
$1,220
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $31,190 | $84,160 |
$6,110
102,700
kWh
|
$5,560
-
kW-mo/yr
|
$(-1,400.0)
-
MMBtu
|
$20,920
-
MMBtu
|
||
TOTAL IMPLEMENTED | $16,090 | $35,190 |
$2,880
48,400
kWh
|
$1,220
-
kW-mo/yr
|
$(-1,400.0)
-
MMBtu
|
$13,390
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs