| Assessment Year | 2010 |
|---|---|
| Principal Product | Dry mix cement and concrete products |
| NAICS | 327999: All Other Miscellaneous Nonmetallic Mineral Product Manufacturing |
| SIC | 3272: Concrete Products, Except Block and Brick |
| Sales Range | $10 M to 50M |
| # of Employees | 71 |
| Plant Area |
47,720
ft2
|
| Annual Production | 6,120,000
pieces
|
| Production Hrs. Annual | 4,512
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $67,591 | 1,930,560 |
kWh
|
$0.035 |
| Electricity Demand | $104,160 | 6,508 |
kW-mo/yr
|
$16.00 |
| Electricity Fees | $719 | - |
|
- |
| Natural Gas | $139,005 | 32,286 |
MMBtu
|
$4.31 |
| LPG | $33,161 | 2,132 |
MMBtu
|
$15.55 |
| Fuel Oil #2 | $12,547 | 849 |
MMBtu
|
$14.78 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $19,960 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,110 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,340 | $2,810 |
$1,820
40,900
kWh
|
$2,520
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,430 | $1,000 |
$1,260
28,300
kWh
|
$2,170
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4133: Use most efficient type of electric motors | $1,750 | $7,500 |
$730
16,300
kWh
|
$1,020
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.2511: Insulate bare equipment | $1,210 | $430 | - | - |
$1,210
-
MMBtu
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,680 | $25,000 |
$2,700
60,800
kWh
|
$2,640
-
kW-mo/yr
|
- | $70 | $270 | |
| 06 | 2.9114: Use solar heat to make electricty | $3,550 | $21,000 |
$1,300
29,200
kWh
|
$2,250
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $19,960 | $57,740 |
$7,810
175,500
kWh
|
$10,600
-
kW-mo/yr
|
$1,210
-
MMBtu
|
$70 | $270 | ||
| TOTAL IMPLEMENTED | $9,110 | $26,000 |
$3,960
89,100
kWh
|
$4,810
-
kW-mo/yr
|
- | $70 | $270 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs