ITAC Assessment: CO0630
ITAC logo
ITAC Assessment: CO0630
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Asphalt paving mixtures
NAICS 324121: Asphalt Paving Mixture and Block Manufacturing
SIC 2951: Asphalt Paving Mixtures and Blocks
Sales Range $10
M
to 50
M
# of Employees 6
Plant Area 52,500
ft2
Annual Production 450,000
ton
Production Hrs. Annual 2,389
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $237,409 1,899,263
kWh
Natural Gas $321,202 45,690
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $68,610 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $47,380 $46,700 $47,380
379,000
kWh
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $9,410 $2,000 $9,410
75,300
kWh
-
03 2.2515: Use optimum thickness insulation $8,920 $12,000 - $8,920
-
MMBtu
04 2.4133: Use most efficient type of electric motors $1,070 $9,010 $1,070
8,600
kWh
-
05 2.9114: Use solar heat to make electricty $1,830 $10,599 $1,830
14,600
kWh
-
TOTAL RECOMMENDED $68,610 $80,309 $59,690
477,500
kWh
$8,920
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs