Assessment Year | 2009 |
---|---|
Principal Product | Telephone directories |
NAICS | 511140: Directory and Mailing List Publishers |
SIC | 2741: Miscellaneous Publishing |
Sales Range | $100 M to 500M |
# of Employees | 250 |
Plant Area |
285,000
ft2
|
Annual Production | 75,000,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $713,176 | 20,848,510 |
kWh
|
$0.034 |
Electricity Demand | $589,743 | 38,958 |
kW-mo/yr
|
$15.14 |
Electricity Fees | $1,863 | - |
|
- |
Natural Gas | $88,569 | 17,255 |
MMBtu
|
$5.13 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $58,650 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4239: Eliminate or reduce compressed air usage | $25,070 | $9,190 |
$15,770
463,000
kWh
|
$9,300
-
kW-mo/yr
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,160 | $1,690 |
$9,130
267,900
kWh
|
$6,030
-
kW-mo/yr
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,330 | $1,540 |
$5,490
161,200
kWh
|
$3,630
-
kW-mo/yr
|
$1,120 | - | $3,090 | |
04 | 2.7135: Install occupancy sensors | $1,940 | $1,400 |
$1,490
43,700
kWh
|
- | $450 | - | - | |
05 | 2.7131: Add area lighting switches | $1,530 | $320 |
$520
15,100
kWh
|
$640
-
kW-mo/yr
|
$230 | - | $140 | |
06 | 2.9114: Use solar heat to make electricty | $1,260 | $3,500 |
$500
14,600
kWh
|
$760
-
kW-mo/yr
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $360 | $1,450 |
$120
3,500
kWh
|
$80
-
kW-mo/yr
|
$30 | $130 | - | |
TOTAL RECOMMENDED | $58,650 | $19,090 |
$33,020
969,000
kWh
|
$20,440
-
kW-mo/yr
|
$1,830 | $130 | $3,230 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs