| Assessment Year | 2008 |
|---|---|
| Principal Product | Fabricated glass products |
| NAICS | 327215: Glass Product Manufacturing Made of Purchased Glass |
| SIC | 3231: Glass Products, Made of Purchased Glass |
| Sales Range | $5 M to 10M |
| # of Employees | 55 |
| Plant Area |
199,000
ft2
|
| Annual Production | 20,500
thousand feet
|
| Production Hrs. Annual | 4,680
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $50,102 | 1,562,946 |
kWh
|
$0.032 |
| Electricity Demand | $116,921 | 7,373 |
kW-mo/yr
|
$15.86 |
| Electricity Fees | $362 | - |
|
- |
| Natural Gas | $18,869 | 2,174 |
MMBtu
|
$8.68 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $27,220 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,450 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3191: Use demand controller or load shedder | $6,560 | $12,000 | - |
$6,560
-
kW-mo/yr
|
- | - | |
| 02 | 2.6218: Turn off equipment when not in use | $6,490 | $1,000 |
$6,490
139,700
kWh
|
- | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,960 | $1,500 |
$1,260
27,200
kWh
|
$700
-
kW-mo/yr
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,280 | $13,730 |
$5,890
126,900
kWh
|
$4,360
-
kW-mo/yr
|
$200 | $(-170.0) | |
| 05 | 2.9114: Use solar heat to make electricty | $1,930 | $11,000 |
$680
14,600
kWh
|
$1,250
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $27,220 | $39,230 |
$14,320
308,400
kWh
|
$12,870
-
kW-mo/yr
|
$200 | $(-170.0) | ||
| TOTAL IMPLEMENTED | $8,450 | $2,500 |
$7,750
166,900
kWh
|
$700
-
kW-mo/yr
|
- | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs