| Assessment Year | 2008 |
|---|---|
| Principal Product | Fabricated glass products |
| NAICS | 327215: Glass Product Manufacturing Made of Purchased Glass |
| SIC | 3231: Glass Products, Made of Purchased Glass |
| Sales Range | $10 M to 50M |
| # of Employees | 144 |
| Plant Area |
84,300
ft2
|
| Annual Production | 5,400,000
lb
|
| Production Hrs. Annual | 7,975
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $267,487 | 8,278,441 |
kWh
|
$0.032 |
| Electricity Demand | $380,205 | 24,519 |
kW-mo/yr
|
$15.51 |
| Electricity Fees | $357 | - |
|
- |
| Natural Gas | $30,873 | 3,778 |
MMBtu
|
$8.17 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $51,550 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $23,410 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,560 | $23,950 |
$5,560
156,500
kWh
|
- | - | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,550 | $200 |
$2,630
74,000
kWh
|
$1,920
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4133: Use most efficient type of electric motors | $500 | $1,755 |
$300
8,349
kWh
|
$200
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.2437: Recover waste heat from equipment | $20,810 | $33,480 | - | - |
$20,810
-
MMBtu
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $18,360 | $20,290 |
$11,610
326,800
kWh
|
$6,740
-
kW-mo/yr
|
- | $450 | $(-440.0) | |
| 06 | 2.9114: Use solar heat to make electricty | $1,770 | $11,000 |
$520
14,600
kWh
|
$1,250
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $51,550 | $90,675 |
$20,620
580,249
kWh
|
$10,110
-
kW-mo/yr
|
$20,810
-
MMBtu
|
$450 | $(-440.0) | ||
| TOTAL IMPLEMENTED | $23,410 | $22,245 |
$14,540
409,149
kWh
|
$8,860
-
kW-mo/yr
|
- | $450 | $(-440.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs