Assessment Year | 2008 |
---|---|
Principal Product | Packaged teas |
NAICS | 311999: All Other Miscellaneous Food Manufacturing |
SIC | 2099: Food Preparations, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 220 |
Plant Area |
155,000
ft2
|
Annual Production | 5,800,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $132,886 | 3,936,000 |
kWh
|
$0.034 |
Electricity Demand | $149,878 | 9,389 |
kW-mo/yr
|
$15.96 |
Electricity Fees | $2,062 | - |
|
- |
Natural Gas | $30,729 | 3,671 |
MMBtu
|
$8.37 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $9,071 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,331 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,170 | $300 |
$1,850
55,500
kWh
|
$2,320
-
kW-mo/yr
|
- | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,370 | $60 |
$750
22,600
kWh
|
$620
-
kW-mo/yr
|
- | - | |
03 | 2.4133: Use most efficient type of electric motors | $161 | $846 |
$79
2,380
kWh
|
$82
-
kW-mo/yr
|
- | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $580 | $4,570 |
$290
8,800
kWh
|
$290
-
kW-mo/yr
|
- | - | |
05 | 2.9114: Use solar heat to make electricty | $1,530 | $11,000 |
$490
14,600
kWh
|
$1,040
-
kW-mo/yr
|
- | - | |
06 | 2.7135: Install occupancy sensors | $1,260 | $2,160 |
$760
22,900
kWh
|
$370
-
kW-mo/yr
|
$40 | $90 | |
TOTAL RECOMMENDED | $9,071 | $18,936 |
$4,219
126,780
kWh
|
$4,722
-
kW-mo/yr
|
$40 | $90 | ||
TOTAL IMPLEMENTED | $4,331 | $1,146 |
$1,929
57,880
kWh
|
$2,402
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs