ITAC Assessment: CO0609
ITAC logo
ITAC Assessment: CO0609
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Packaged teas
NAICS 311999: All Other Miscellaneous Food Manufacturing
SIC 2099: Food Preparations, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 220
Plant Area 155,000
ft2
Annual Production 5,800,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $132,886 3,936,000
kWh
Electricity Demand $149,878 9,389
kW-mo/yr
Electricity Fees $2,062 -
Natural Gas $30,729 3,671
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,071 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,331

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,170 $300 $1,850
55,500
kWh
$2,320
-
kW-mo/yr
- -
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,370 $60 $750
22,600
kWh
$620
-
kW-mo/yr
- -
03 2.4133: Use most efficient type of electric motors $161 $846 $79
2,380
kWh
$82
-
kW-mo/yr
- -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $580 $4,570 $290
8,800
kWh
$290
-
kW-mo/yr
- -
05 2.9114: Use solar heat to make electricty $1,530 $11,000 $490
14,600
kWh
$1,040
-
kW-mo/yr
- -
06 2.7135: Install occupancy sensors $1,260 $2,160 $760
22,900
kWh
$370
-
kW-mo/yr
$40 $90
TOTAL RECOMMENDED $9,071 $18,936 $4,219
126,780
kWh
$4,722
-
kW-mo/yr
$40 $90
TOTAL IMPLEMENTED $4,331 $1,146 $1,929
57,880
kWh
$2,402
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs