Assessment Year | 2006 |
---|---|
Principal Product | Printed circuit boards |
NAICS | 334412: Bare Printed Circuit Board Manufacturing |
SIC | 3672: Printed Circuit Boards |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
40,776
ft2
|
Annual Production | 1,300,000
pieces
|
Production Hrs. Annual | 4,862
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $77,765 | 1,927,997 |
kWh
|
$0.040 |
Electricity Demand | $101,380 | 7,003 |
kW-mo/yr
|
$14.48 |
Electricity Fees | $1,946 | - |
|
- |
Natural Gas | $23,098 | 2,029 |
MMBtu
|
$11.38 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,100 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,450 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4226: Use / purchase optimum sized compressor | $4,720 | $19,200 |
$2,380
73,300
kWh
|
$2,340
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,820 | $140 |
$990
30,400
kWh
|
$830
-
kW-mo/yr
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,860 | $10,220 |
$1,760
54,300
kWh
|
$1,660
-
kW-mo/yr
|
$50 | $390 | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,620 | $6,660 |
$1,310
40,200
kWh
|
$1,470
-
kW-mo/yr
|
$10 | $(-170.0) | |
05 | 2.9114: Use solar heat to make electricty | $1,360 | $11,000 |
$470
14,600
kWh
|
$890
-
kW-mo/yr
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $630 | $850 |
$100
3,000
kWh
|
$60
-
kW-mo/yr
|
$100 | $370 | |
07 | 2.7135: Install occupancy sensors | $90 | $390 |
$80
2,500
kWh
|
$10
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $15,100 | $48,460 |
$7,090
218,300
kWh
|
$7,260
-
kW-mo/yr
|
$160 | $590 | ||
TOTAL IMPLEMENTED | $2,450 | $990 |
$1,090
33,400
kWh
|
$890
-
kW-mo/yr
|
$100 | $370 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs