Assessment Year | 2005 |
---|---|
Principal Product | Construction equipment |
NAICS | 333120: Construction Machinery Manufacturing |
SIC | 3531: Construction Machinery and Equipment |
Sales Range | greater than $500 M |
# of Employees | 800 |
Plant Area |
367,000
ft2
|
Annual Production | 20,250
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | North Dakota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $843,948 | 35,616,000 |
kWh
|
$0.024 |
Electricity Demand | $402,663 | 63,648 |
kW-mo/yr
|
$6.33 |
Electricity Fees | $83,054 | - |
|
- |
Natural Gas | $815,026 | 119,829 |
MMBtu
|
$6.80 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $457,960 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $277,000 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3416: Use combined cycle gas turbine generator sets with waste heat boilers connected to turbine exhaust | $141,620 | $513,000 |
$106,650
3,878,100
kWh
|
$34,970
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.3212: Optimize plant power factor | $135,890 | $303,800 |
$32,940
1,780,800
kWh
|
$19,900
-
kW-mo/yr
|
$83,050 | - | - | - | |
03 | 2.1122: Re-size charging openings or add a movable door on equipment | $89,400 | $41,000 | - | - | - |
$89,400
-
MMBtu
|
- | - | |
04 | 4.426: Modify workload | $48,020 | $360 |
$1,220
66,600
kWh
|
- | - | - | $46,800 | - | |
05 | 2.2711: Utilize outside air instead of conditioned air for drying | $3,420 | $6,000 |
$2,340
126,300
kWh
|
$1,080
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4133: Use most efficient type of electric motors | $270 | $340 |
$180
9,529
kWh
|
$90
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $810 | $3,070 |
$520
28,500
kWh
|
$290
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $38,530 | $150,890 |
$25,740
1,391,600
kWh
|
$11,920
-
kW-mo/yr
|
- | - | $(-590.0) | $1,460 | |
TOTAL RECOMMENDED | $457,960 | $1,018,460 |
$169,590
7,281,429
kWh
|
$68,250
-
kW-mo/yr
|
$83,050 |
$89,400
-
MMBtu
|
$46,210 | $1,460 | ||
TOTAL IMPLEMENTED | $277,000 | $351,500 |
$36,680
1,983,229
kWh
|
$21,070
-
kW-mo/yr
|
$83,050 |
$89,400
-
MMBtu
|
$46,800 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs