| Assessment Year | 2005 |
|---|---|
| Principal Product | Wood doors & architectural millwork |
| NAICS | 321911: Wood Window and Door Manufacturing |
| SIC | 2431: Millwork |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
68,000
ft2
|
| Annual Production | 26,000
pieces
|
| Production Hrs. Annual | 2,210
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $42,910 | 898,200 |
kWh
|
$0.048 |
| Electricity Demand | $52,946 | 3,809 |
kW-mo/yr
|
$13.90 |
| Natural Gas | $14,520 | 1,755 |
MMBtu
|
$8.27 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $423,400 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $345,470 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.132: Purchase new equipment to reduce material use / cost | $329,210 | $400,000 | - | - | - | - |
$29,210
-
lb
|
- | $300,000 | - | |
| 02 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $62,190 | $230,000 |
$20,740
306,900
kWh
|
$8,650
-
kW-mo/yr
|
$13,530
-
MMBtu
|
- |
$19,270
-
lb
|
- | - | - | |
| 03 | 3.8125: Remove rollers from the machines and clean in a closed solvent cleaner | $4,750 | $1,150 | - | - | - |
$1,050
-
gal
|
- | $610 | - | $3,090 | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,710 | $200 |
$780
15,400
kWh
|
$930
-
kW-mo/yr
|
- | - | - | - | - | - | |
| 05 | 2.4239: Eliminate or reduce compressed air usage | $1,370 | $600 |
$780
15,200
kWh
|
$590
-
kW-mo/yr
|
- | - | - | - | - | - | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $670 | $1,290 |
$280
5,400
kWh
|
$390
-
kW-mo/yr
|
- | - | - | - | - | - | |
| 07 | 2.7145: Install skylights | $12,750 | $90,400 |
$5,990
117,400
kWh
|
$6,340
-
kW-mo/yr
|
- | - | - | $190 | - | $230 | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,270 | $4,000 |
$3,220
63,100
kWh
|
$3,820
-
kW-mo/yr
|
- | - | - | $120 | - | $110 | |
| 09 | 2.9111: Use solar heat to heat make-up air | $2,170 | $23,570 |
$(-200.0)
(-4,000)
kWh
|
$(-140.0)
-
kW-mo/yr
|
$2,510
-
MMBtu
|
- | - | - | - | - | |
| 10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $760 | $1,050 |
$320
6,300
kWh
|
$420
-
kW-mo/yr
|
- | - | - | $10 | - | $10 | |
| 11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $400 | $440 |
$90
1,800
kWh
|
$30
-
kW-mo/yr
|
- | - | - | $60 | - | $220 | |
| 12 | 2.7135: Install occupancy sensors | $150 | $390 |
$150
3,000
kWh
|
- | - | - | - | - | - | - | |
| TOTAL RECOMMENDED | $423,400 | $753,090 |
$32,150
530,500
kWh
|
$21,030
-
kW-mo/yr
|
$16,040
-
MMBtu
|
$1,050
-
gal
|
$48,480
-
lb
|
$990 | $300,000 | $3,660 | ||
| TOTAL IMPLEMENTED | $345,470 | $407,440 |
$5,190
101,800
kWh
|
$5,790
-
kW-mo/yr
|
- |
$1,050
-
gal
|
$29,210
-
lb
|
$800 | $300,000 | $3,430 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs