ITAC Assessment: CO0572
ITAC logo
ITAC Assessment: CO0572
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Aircraft
NAICS 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 400
Plant Area 90,000
ft2
Annual Production 7
pieces
Production Hrs. Annual 6,916
hrs
Location (State) New Mexico

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $115,357 1,752,960
kWh
Electricity Demand $11,817 3,540
kW-mo/yr
Electricity Fees $2,392 -
Natural Gas $6,747 775
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,950 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7145: Install skylights $9,660 $40,800 $7,150
175,500
kWh
$1,530
-
kW-mo/yr
- $870 $110
02 2.7142: Utilize higher efficiency lamps and/or ballasts $3,460 $7,700 $2,790
68,500
kWh
$390
-
kW-mo/yr
- $140 $140
03 2.9111: Use solar heat to heat make-up air $2,480 $30,770 $(-310.0)
(-7,600)
kWh
$(-80.0)
-
kW-mo/yr
$2,870
-
MMBtu
- -
04 2.7135: Install occupancy sensors $2,420 $7,570 $1,640
40,200
kWh
- - $80 $700
05 2.7243: Improve air circulation with destratification fans / other methods $1,370 $1,000 $(-200.0)
(-4,900)
kWh
$(-30.0)
-
kW-mo/yr
$1,600
-
MMBtu
- -
06 2.7135: Install occupancy sensors $560 $1,760 $560
13,800
kWh
- - - -
TOTAL RECOMMENDED $19,950 $89,600 $11,630
285,500
kWh
$1,810
-
kW-mo/yr
$4,470
-
MMBtu
$1,090 $950
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs