ITAC Assessment: CO0566
ITAC logo
ITAC Assessment: CO0566
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Baked and Par-Baked Breads
NAICS 311812: Commercial Bakeries
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $10
M
to 50
M
# of Employees 170
Plant Area 33,600
ft2
Annual Production 27,000,000
lb
Production Hrs. Annual 7,488
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $82,728 2,457,760
kWh
Electricity Demand $56,120 4,518
kW-mo/yr
Electricity Fees $480 -
Natural Gas $156,973 19,236
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $31,810 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,570

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.2437: Recover waste heat from equipment $2,690 $2,060 - - $2,690
-
MMBtu
- - -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $300 $550 $190
5,400
kWh
$110
-
kW-mo/yr
- - - -
03 2.8114: Change rate schedules or other changes in utility service $11,560 $300 - - - - $11,560 -
04 2.7447: Install vinyl strip / high speed / air curtain doors $7,010 $20,000 $3,770
104,500
kWh
- - $240 - $3,000
05 2.9111: Use solar heat to heat make-up air $5,080 $38,680 - - $5,080
-
MMBtu
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $4,170 $6,180 $2,270
62,900
kWh
$1,660
-
kW-mo/yr
- $120 - $120
07 2.7135: Install occupancy sensors $1,000 $640 $360
10,100
kWh
- - $40 - $600
TOTAL RECOMMENDED $31,810 $68,410 $6,590
182,900
kWh
$1,770
-
kW-mo/yr
$7,770
-
MMBtu
$400 $11,560 $3,720
TOTAL IMPLEMENTED $18,570 $20,300 $3,770
104,500
kWh
- - $240 $11,560 $3,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs