Assessment Year | 2005 |
---|---|
Principal Product | Can Press and Printing Machines |
NAICS | 333517: Machine Tool Manufacturing |
SIC | 3542: Machine Tools, Metal Forming Types |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
93,360
ft2
|
Annual Production | 10
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $53,007 | 1,762,400 |
kWh
|
$0.030 |
Electricity Demand | $53,926 | 4,106 |
kW-mo/yr
|
$13.13 |
Electricity Fees | $192 | - |
|
- |
Natural Gas | $30,216 | 3,830 |
MMBtu
|
$7.89 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $59,500 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $40,350 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,670 | $280 |
$1,060
30,100
kWh
|
$610
-
kW-mo/yr
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $35,290 | $39,650 |
$9,000
255,500
kWh
|
$6,480
-
kW-mo/yr
|
- | $5,840 | $13,970 | |
03 | 2.9111: Use solar heat to heat make-up air | $11,250 | $72,910 | - | - |
$11,250
-
MMBtu
|
- | - | |
04 | 2.7243: Improve air circulation with destratification fans / other methods | $7,290 | $25,470 |
$(-670.0)
(-19,000)
kWh
|
$(-340.0)
-
kW-mo/yr
|
$8,300
-
MMBtu
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,090 | $8,320 |
$750
21,200
kWh
|
$1,140
-
kW-mo/yr
|
- | $70 | $130 | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $870 | $3,510 |
$450
12,900
kWh
|
$330
-
kW-mo/yr
|
- | $(-20.0) | $110 | |
07 | 2.7135: Install occupancy sensors | $610 | $2,380 |
$530
14,900
kWh
|
- | - | $50 | $30 | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $430 | $1,400 |
$40
1,000
kWh
|
$10
-
kW-mo/yr
|
- | $120 | $260 | |
TOTAL RECOMMENDED | $59,500 | $153,920 |
$11,160
316,600
kWh
|
$8,230
-
kW-mo/yr
|
$19,550
-
MMBtu
|
$6,060 | $14,500 | ||
TOTAL IMPLEMENTED | $40,350 | $53,160 |
$11,300
320,700
kWh
|
$8,570
-
kW-mo/yr
|
- | $6,010 | $14,470 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs