| Assessment Year | 2005 |
|---|---|
| Principal Product | Snack foods |
| NAICS | 311919: Other Snack Food Manufacturing |
| SIC | 2096: Potato Chips, Corn Chips, and Similar Snacks |
| Sales Range | $1 M to 5M |
| # of Employees | 100 |
| Plant Area |
100,000
ft2
|
| Annual Production | 5,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $34,950 | 1,222,897 |
kWh
|
$0.029 |
| Electricity Demand | $55,452 | 3,865 |
kW-mo/yr
|
$14.35 |
| Electricity Fees | $1,611 | - |
|
- |
| Natural Gas | $257,514 | 42,876 |
MMBtu
|
$6.01 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $34,750 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,300 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $15,350 | $10,080 | - | - |
$15,350
-
MMBtu
|
- | - | - | - | |
| 02 | 3.4111: Use closed cycle process to minimize waste water production | $10,710 | $1,080 |
$(-20.0)
(-600)
kWh
|
$(-70.0)
-
kW-mo/yr
|
- |
$8,780
-
Tgal
|
- | - |
$2,020
-
Tgal
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,500 | $240 |
$760
26,500
kWh
|
$740
-
kW-mo/yr
|
- | - | - | - | - | |
| 04 | 2.2711: Utilize outside air instead of conditioned air for drying | $150 | $120 |
$80
2,800
kWh
|
$70
-
kW-mo/yr
|
- | - | - | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,290 | $13,190 |
$1,820
63,500
kWh
|
$2,040
-
kW-mo/yr
|
- | - | $(-100.0) | $530 | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,530 | $2,350 |
$740
25,800
kWh
|
$730
-
kW-mo/yr
|
- | - | - | $60 | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,120 | $430 |
$380
13,300
kWh
|
$730
-
kW-mo/yr
|
- | - | $10 | - | - | |
| 08 | 2.7135: Install occupancy sensors | $100 | $390 |
$100
3,400
kWh
|
- | - | - | - | - | - | |
| TOTAL RECOMMENDED | $34,750 | $27,880 |
$3,860
134,700
kWh
|
$4,240
-
kW-mo/yr
|
$15,350
-
MMBtu
|
$8,780
-
Tgal
|
$(-90.0) | $590 |
$2,020
-
Tgal
|
||
| TOTAL IMPLEMENTED | $4,300 | $3,140 |
$1,960
68,400
kWh
|
$2,270
-
kW-mo/yr
|
- | - | $10 | $60 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs