ITAC Assessment: CO0562
ITAC logo
ITAC Assessment: CO0562
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Snack foods
NAICS 311919: Other Snack Food Manufacturing
SIC 2096: Potato Chips, Corn Chips, and Similar Snacks
Sales Range $1
M
to 5
M
# of Employees 100
Plant Area 100,000
ft2
Annual Production 5,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $34,950 1,222,897
kWh
Electricity Demand $55,452 3,865
kW-mo/yr
Electricity Fees $1,611 -
Natural Gas $257,514 42,876
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $34,750 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,300

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.1121: Use insulation in furnaces to facilitate heating / cooling $15,350 $10,080 - - $15,350
-
MMBtu
- - - -
02 3.4111: Use closed cycle process to minimize waste water production $10,710 $1,080 $(-20.0)
(-600)
kWh
$(-70.0)
-
kW-mo/yr
- $8,780
-
Tgal
- - $2,020
-
Tgal
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,500 $240 $760
26,500
kWh
$740
-
kW-mo/yr
- - - - -
04 2.2711: Utilize outside air instead of conditioned air for drying $150 $120 $80
2,800
kWh
$70
-
kW-mo/yr
- - - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $4,290 $13,190 $1,820
63,500
kWh
$2,040
-
kW-mo/yr
- - $(-100.0) $530 -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,530 $2,350 $740
25,800
kWh
$730
-
kW-mo/yr
- - - $60 -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $1,120 $430 $380
13,300
kWh
$730
-
kW-mo/yr
- - $10 - -
08 2.7135: Install occupancy sensors $100 $390 $100
3,400
kWh
- - - - - -
TOTAL RECOMMENDED $34,750 $27,880 $3,860
134,700
kWh
$4,240
-
kW-mo/yr
$15,350
-
MMBtu
$8,780
-
Tgal
$(-90.0) $590 $2,020
-
Tgal
TOTAL IMPLEMENTED $4,300 $3,140 $1,960
68,400
kWh
$2,270
-
kW-mo/yr
- - $10 $60 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs