Assessment Year | 2004 |
---|---|
Principal Product | Pressure sensitive tape |
NAICS | 322220: Paper Bag and Coated and Treated Paper Manufacturing |
SIC | 2672: Coated and Laminated Paper, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 90 |
Plant Area |
400,000
ft2
|
Annual Production | 133,000,000
thousand feet
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $460,227 | 14,863,000 |
kWh
|
$0.031 |
Electricity Demand | $419,173 | 37,333 |
kW-mo/yr
|
$11.23 |
Electricity Fees | $1,479 | - |
|
- |
Natural Gas | $486,631 | 107,967 |
MMBtu
|
$4.51 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $81,920 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $28,410 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3412: Use waste heat to produce steam to drive a steam turbine-generator | $29,210 | $116,000 |
$13,410
650,800
kWh
|
$15,800
-
kW-mo/yr
|
- | - | |
02 | 2.2414: Use waste heat from hot flue gases to preheat | $12,000 | $27,900 | - | - |
$12,000
-
MMBtu
|
- | |
03 | 2.2437: Recover waste heat from equipment | $6,130 | $3,800 | - | - |
$6,130
-
MMBtu
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,920 | $510 |
$2,720
132,000
kWh
|
$3,200
-
kW-mo/yr
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,780 | $60 |
$2,180
106,040
kWh
|
$3,600
-
kW-mo/yr
|
- | - | |
06 | 2.6242: Minimize operation of equipment maintained in standby condition | $650 | $500 |
$650
31,700
kWh
|
- | - | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $390 | $360 |
$180
8,800
kWh
|
$210
-
kW-mo/yr
|
- | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $21,840 | $58,140 |
$12,370
600,400
kWh
|
$14,580
-
kW-mo/yr
|
- | $(-5,110.0) | |
TOTAL RECOMMENDED | $81,920 | $207,270 |
$31,510
1,529,740
kWh
|
$37,390
-
kW-mo/yr
|
$18,130
-
MMBtu
|
$(-5,110.0) | ||
TOTAL IMPLEMENTED | $28,410 | $59,150 |
$15,740
764,100
kWh
|
$17,780
-
kW-mo/yr
|
- | $(-5,110.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs