ITAC Assessment: CO0546
ITAC logo
ITAC Assessment: CO0546
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Eggs, Fertilizer, and Wood Mulch
NAICS 325314: Fertilizer (Mixing Only) Manufacturing
SIC 2875: Fertilizers, Mixing Only
Sales Range $50
M
to 100
M
# of Employees 85
Plant Area 150,000
ft2
Annual Production 50,000
ton
Production Hrs. Annual 3,120
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $144,136 5,423,137
kWh
Electricity Demand $174,002 17,323
kW-mo/yr
Electricity Fees $1,794 -
Natural Gas $323,795 69,951
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $59,374 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,424

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.2711: Utilize outside air instead of conditioned air for drying $53,860 $348,900 $1,120
42,500
kWh
$(-7,050.0)
-
kW-mo/yr
$46,790
-
MMBtu
$13,000
02 2.4133: Use most efficient type of electric motors $974 $2,964 $411
15,601
kWh
$563
-
kW-mo/yr
- -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,310 $7,930 $1,580
60,000
kWh
$730
-
kW-mo/yr
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,450 $110 $550
21,000
kWh
$900
-
kW-mo/yr
- -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $780 $4,870 $240
9,200
kWh
$540
-
kW-mo/yr
- -
TOTAL RECOMMENDED $59,374 $364,774 $3,901
148,301
kWh
$(-4,317.0)
-
kW-mo/yr
$46,790
-
MMBtu
$13,000
TOTAL IMPLEMENTED $2,424 $3,074 $961
36,601
kWh
$1,463
-
kW-mo/yr
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs