Assessment Year | 2003 |
---|---|
Principal Product | soft drinks |
NAICS | 312111: Soft Drink Manufacturing |
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $100 M to 500M |
# of Employees | 650 |
Plant Area |
616,684
ft2
|
Annual Production | 30,000,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $304,911 | 14,011,271 |
kWh
|
$0.022 |
Electricity Demand | $417,155 | 31,370 |
kW-mo/yr
|
$13.30 |
Electricity Fees | $384 | - |
|
- |
Natural Gas | $285,537 | 47,780 |
MMBtu
|
$5.98 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $166,899 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $46,114 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $63,500 | $148,580 | n/a |
$48,240
1,503,400
kWh
|
$28,060
-
kW-mo/yr
|
- | - | - | $(-12,800.0) | - |
02 | 2.7135: Install occupancy sensors | $17,410 | $63,410 |
$9,770
304,200
kWh
|
$5,610
-
kW-mo/yr
|
- | - | $980 | $1,050 | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $16,760 | $310 |
$10,680
332,600
kWh
|
$6,080
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.1222: Install turbulators | $12,720 | $8,820 | - | - |
$8,980
-
MMBtu
|
- | $240 | $3,500 | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,454 | $4,810 |
$11,097
345,819
kWh
|
$6,449
-
kW-mo/yr
|
- | - | - | $(-3,092.0) | - | |
06 | 2.4133: Use most efficient type of electric motors | $1,495 | $2,618 |
$939
29,265
kWh
|
$556
-
kW-mo/yr
|
- | - | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,670 | $4,320 |
$660
20,600
kWh
|
$370
-
kW-mo/yr
|
- | - | $850 | $790 | - | |
08 | 2.2135: Repair and eliminate steam leaks | $1,280 | $220 | - | - |
$1,280
-
MMBtu
|
- | - | - | - | |
09 | 2.7141: Lower light fixtures in high ceiling areas | $980 | $1,200 |
$620
19,400
kWh
|
$360
-
kW-mo/yr
|
- | - | - | - | - | |
10 | 2.7135: Install occupancy sensors | $460 | $390 |
$230
7,200
kWh
|
$200
-
kW-mo/yr
|
- | - | $20 | $10 | - | |
11 | 3.4113: Treat and reuse rinse waters | $31,660 | $19,160 |
$(-410.0)
(-12,800)
kWh
|
$(-270.0)
-
kW-mo/yr
|
- |
$26,130
-
Tgal
|
- | - |
$6,210
-
Tgal
|
|
12 | 3.5317: Sell / offer by-product as animal feed | $3,510 | $11,830 |
$(-70.0)
(-2,100)
kWh
|
$(-130.0)
-
kW-mo/yr
|
- |
$3,710
-
Tgal
|
- | - | - | |
TOTAL RECOMMENDED | $166,899 | $265,668 |
$81,756
2,547,584
kWh
|
$47,285
-
kW-mo/yr
|
$10,260
-
MMBtu
|
$29,840
-
Tgal
|
$2,090 | $(-10,542.0) |
$6,210
-
Tgal
|
||
TOTAL IMPLEMENTED | $46,114 | $23,970 |
$10,687
333,019
kWh
|
$6,179
-
kW-mo/yr
|
- |
$26,130
-
Tgal
|
- | $(-3,092.0) |
$6,210
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs