ITAC Assessment: CO0531
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product soft drinks
NAICS 312111: Soft Drink Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $100
M
to 500
M
# of Employees 650
Plant Area 616,684
ft2
Annual Production 30,000,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $304,911 14,011,271
kWh
Electricity Demand $417,155 31,370
kW-mo/yr
Electricity Fees $384 -
Natural Gas $285,537 47,780
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $166,899 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $46,114

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $63,500 $148,580 n/a $48,240
1,503,400
kWh
$28,060
-
kW-mo/yr
- - - $(-12,800.0) -
02 2.7135: Install occupancy sensors $17,410 $63,410 $9,770
304,200
kWh
$5,610
-
kW-mo/yr
- - $980 $1,050 -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $16,760 $310 $10,680
332,600
kWh
$6,080
-
kW-mo/yr
- - - - -
04 2.1222: Install turbulators $12,720 $8,820 - - $8,980
-
MMBtu
- $240 $3,500 -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $14,454 $4,810 $11,097
345,819
kWh
$6,449
-
kW-mo/yr
- - - $(-3,092.0) -
06 2.4133: Use most efficient type of electric motors $1,495 $2,618 $939
29,265
kWh
$556
-
kW-mo/yr
- - - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $2,670 $4,320 $660
20,600
kWh
$370
-
kW-mo/yr
- - $850 $790 -
08 2.2135: Repair and eliminate steam leaks $1,280 $220 - - $1,280
-
MMBtu
- - - -
09 2.7141: Lower light fixtures in high ceiling areas $980 $1,200 $620
19,400
kWh
$360
-
kW-mo/yr
- - - - -
10 2.7135: Install occupancy sensors $460 $390 $230
7,200
kWh
$200
-
kW-mo/yr
- - $20 $10 -
11 3.4113: Treat and reuse rinse waters $31,660 $19,160 $(-410.0)
(-12,800)
kWh
$(-270.0)
-
kW-mo/yr
- $26,130
-
Tgal
- - $6,210
-
Tgal
12 3.5317: Sell / offer by-product as animal feed $3,510 $11,830 $(-70.0)
(-2,100)
kWh
$(-130.0)
-
kW-mo/yr
- $3,710
-
Tgal
- - -
TOTAL RECOMMENDED $166,899 $265,668 $81,756
2,547,584
kWh
$47,285
-
kW-mo/yr
$10,260
-
MMBtu
$29,840
-
Tgal
$2,090 $(-10,542.0) $6,210
-
Tgal
TOTAL IMPLEMENTED $46,114 $23,970 $10,687
333,019
kWh
$6,179
-
kW-mo/yr
- $26,130
-
Tgal
- $(-3,092.0) $6,210
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs