Assessment Year | 2003 |
---|---|
Principal Product | Hard surfacing and brazing alloys |
NAICS | 331492: Secondary Smelting, Refining, and Alloying of Nonferrous Metal (except Copper and Aluminum) |
SIC | 3341: Secondary Smelting and Refining of Nonferrous Metals |
Sales Range | $10 M to 50M |
# of Employees | 44 |
Plant Area |
52,767
ft2
|
Annual Production | 2,160,000
lb
|
Production Hrs. Annual | 3,120
hrs
|
Location (State) | New Mexico |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $104,254 | 2,317,200 |
kWh
|
$0.045 |
Electricity Demand | $125,914 | 16,950 |
kW-mo/yr
|
$7.43 |
Electricity Fees | $68,988 | - |
|
- |
Natural Gas | $25,839 | 4,430 |
MMBtu
|
$5.83 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $59,914 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $47,904 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $41,400 | $7,000 | - |
$41,400
-
kW-mo/yr
|
- | |
02 | 2.4234: Cool compressor air intake with heat exchanger | $5,520 | $5,060 |
$2,120
42,300
kWh
|
$3,400
-
kW-mo/yr
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,790 | $16,530 |
$2,640
56,600
kWh
|
$2,690
-
kW-mo/yr
|
$(-540.0) | |
04 | 2.4237: Substitute compressed air cooling with water or air cooling | $3,810 | $3,920 |
$1,880
40,100
kWh
|
$1,930
-
kW-mo/yr
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,090 | $190 |
$780
16,200
kWh
|
$1,310
-
kW-mo/yr
|
- | |
06 | 2.4239: Eliminate or reduce compressed air usage | $1,240 | $4,000 |
$1,240
24,800
kWh
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $386 | $128 |
$206
4,448
kWh
|
$211
-
kW-mo/yr
|
$(-31.0) | |
08 | 2.4133: Use most efficient type of electric motors | $218 | $250 |
$111
2,425
kWh
|
$107
-
kW-mo/yr
|
- | |
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $460 | $1,440 |
$230
5,100
kWh
|
$230
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $59,914 | $38,518 |
$9,207
191,973
kWh
|
$51,278
-
kW-mo/yr
|
$(-571.0) | ||
TOTAL IMPLEMENTED | $47,904 | $11,488 |
$2,977
63,173
kWh
|
$44,958
-
kW-mo/yr
|
$(-31.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs