ITAC Assessment: CO0527
ITAC logo
ITAC Assessment: CO0527
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Solid surface materials
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 86,000
ft2
Annual Production 10,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) New Mexico

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $154,194 3,743,298
kWh
Electricity Demand $75,235 11,071
kW-mo/yr
Electricity Fees $69,146 -
Natural Gas $62,989 11,530
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $23,287 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $11,000 $15,440 $6,500
157,800
kWh
$3,930
-
kW-mo/yr
- $570
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,260 $550 $6,390
155,000
kWh
$3,870
-
kW-mo/yr
- -
03 2.4133: Use most efficient type of electric motors $467 $518 $246
5,182
kWh
$221
-
kW-mo/yr
- -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $960 $2,310 $560
13,600
kWh
$400
-
kW-mo/yr
- -
05 2.2511: Insulate bare equipment $600 $1,270 - - $600
-
MMBtu
-
TOTAL RECOMMENDED $23,287 $20,088 $13,696
331,582
kWh
$8,421
-
kW-mo/yr
$600
-
MMBtu
$570
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs